Shottermill Feeder Diversion
Project Overview & Date of Works
-
15/11/2025 to 16/11/2025 & 22/11/2025 to 23/11/2025
-
2 33kv oil-filled cable to XLPE cable transition joints
-
2 Sets of Eaton T-Boot style terminations
-
Cutting and draining of the oil-filled cable, and the disconnection of existing oil-filled cable ceiling end terminations



Challenges
-
Dealing with an existing cross between phases
-
Working in bad weather conditions
-
Ensuring no harmful oil got into the environment whilst draining and cutting oil-filled cables and terminations
Solutions
-
Working alongside Network rail, Level A qualified persons carrying numerous different phase checks
-
All ADY-HV jointing teams are equipped with ShearSpeed shelters and umbrellas to keep all terminations and joints dry – Allowing projects to continuously move forward even in bad weather conditions
-
Ady-HV operatives set up a spill kit and placed down oil absorbent mats to make sure no harmful oil that was spilt was left to damage the environment around us