Oriel Eye Hospital

Project Overview & Date of Works

  • 2026
  • 18x 11KV 240mm 3 core cable terminations
  • 3x 11KV 300mm single core cable termination UKPN incomer

Challenges

  • Strict bending radius of cables
  • Leasing with panel installers for Switchgear modifications to enable terminations to be installed
  • Leased with cable pulling gangs to establish a safe and effective plan

Solutions

  • After leasing with the panel installers the team came up with some modification ideas in order to comply with the strict bending radius requirements of the cables on site. As well as this, Ady-HV operatives leased with the onsite cable pulling gangs to ensure the cables were pulled in an order to ensure works could progress effectively and safely.